sectors : Offices
  • The work will last for 2 years and 4 months
  • Scale of the work is more than $14 500 000.00
  • Montreal, Quebec
    • Complete installation of an air conditioning system for a 50-storey office tower
    • In addition to an artificial skating rink in the central atrium
    • Ion

other Projects

CHUM - University of Montreal Hospital Centre

Phase 1 B-4 to B-1, and P1 to P5. Technical and mechanical work for phase 1 was carried out in the D Block, consisting of rooms for medical consultations, medical examinations, minor surgery and MRI scans, as well as parking areas.

MUHC - McGill University Health Center

Hospital consisting of more than one building, for a total of 10 storeys, requiring the installation of high-performance HVAC (heating, ventilation and air conditioning) systems, with high levels of filtration, allowing air to be treated up to a 100%

Casino de Montréal

Cold room redevelopment; Casiloc modernization project. Parallel pack.