sectors : Food Processing and Warehouse
  • The work will last for 3 months
  • Scale of the work is more than $500 000.00
  • Drummondville, Quebec
    • Addition of (9) nine evaporator
    • Refrigeration for meat freezer
    • Optimisation of valves stations
    • Accelerated works requiring a ‘’Shut down’’
    • Hot gas defrost

     

other Projects

Du Boisé Library

New installation of several ventilation systems for the entire building. LEED-NC, v.1.0, Gold-certified building.

St-Mary Hospital Center

Installation of a redundant 400 tons refrigeration unit.

CHUM - University of Montreal Hospital Centre

Phase 1 B-4 to B-1, and P1 to P5. Technical and mechanical work for phase 1 was carried out in the D Block, consisting of rooms for medical consultations, medical examinations, minor surgery and MRI scans, as well as parking areas.