Installation of a redundant 400 tons refrigeration unit.
Phase 1 B-4 to B-1, and P1 to P5. Technical and mechanical work for phase 1 was carried out in the D Block, consisting of rooms for medical consultations, medical examinations, minor surgery and MRI scans, as well as parking areas.
Replacement of the building’s cooling towers. Air-lifted into place by a helicopter fitted out specifically for this type of work.