sectors : Industrial
  • The work last for 5 months
  • Scale of the work is more than $400 000.00
  • Terrebonne, Québec
  • New steel and metal surfaces’ treatment facility. ADF Group is a major producer of complex metal structure elements. This new facility will will allow the handling of oversized structural elements.

    Characteristics

    • Construction of the ventilation system with the constraints of overhead cranes on the whole surface of the plant.
    • Ventilation system 100% fresh air / 100% exhaust with a total capacity of 92 000 CFM.
    • Four evacuation chimneys of 25 metres high.
    • Ventilation of a compressor room with heat recovery.

other Projects

1000 de la gauchetière

Complete installation of an air conditioning system for a 50-storey office tower, in addition to an artificial skating rink in the central atrium.

Cummins Diesel

Office air conditioning and carbon monoxide removal.

Du Boisé Library

New installation of several ventilation systems for the entire building. LEED-NC, v.1.0, Gold-certified building.

Facebook
LinkedIn