sectors : Lab Works
  • The work will last for 3 months
  • Scale of the work is more than $250 000.00
  • Montreal, Quebec
    • Full ductwork for R&D labs. C building
    • Project planning was made to be sure that 90% of the work, including pressure test for ventilation ducks and thermal insulation, would be completed during the summer construction holidays (2 weeks)
    • Installation and delivery of HEPA filters, including DOP test and laboratory validation.