sectors : Industrial
  • The work last for 5 months
  • Scale of the work is more than $400 000.00
  • Terrebonne, Québec
  • New steel and metal surfaces’ treatment facility. ADF Group is a major producer of complex metal structure elements. This new facility will will allow the handling of oversized structural elements.

    Characteristics

    • Construction of the ventilation system with the constraints of overhead cranes on the whole surface of the plant.
    • Ventilation system 100% fresh air / 100% exhaust with a total capacity of 92 000 CFM.
    • Four evacuation chimneys of 25 metres high.
    • Ventilation of a compressor room with heat recovery.

other Projects

CHUM - University of Montreal Hospital Centre

Phase 1 B-4 to B-1, and P1 to P5. Technical and mechanical work for phase 1 was carried out in the D Block, consisting of rooms for medical consultations, medical examinations, minor surgery and MRI scans, as well as parking areas.

Caisse de dépôt et placement

Prestigious building with an air conditioning system featuring the latest technologies.

Agropur

We added 12.00 tons of refrigeration to preserve the fine cheese inventory.