sectors : Institutional
  • The work will last for 6 months
  • Scale of the work is more than $700 000.00
  • Montreal, Quebec
    • Installation of a redundant 400 tons refrigeration units.
    • Challenge : incorporation of a cooler in a very small place located in the mechanical room (required custom engineering plans)
    • A lot of coordination : no period with no air conditioning where tolerated

other Projects

1000 de la gauchetière

Complete installation of an air conditioning system for a 50-storey office tower, in addition to an artificial skating rink in the central atrium.

Caisse de dépôt et placement

Prestigious building with an air conditioning system featuring the latest technologies.

Pfizer

Full ductwork for R&D labs. C building.

Facebook
LinkedIn