sectors : Food Processing and Warehouse
  • The work will last for 6 months
  • Scale of the work is more than $1 600 000.00
  • St-Laurent, Quebec
    • New warehouse with 384 tons of refrigeration
    • 40 evaporators with hot gas defrost cool the distribution center
    • The freezer is maintained at -18C and the rest is at 4 C.
    • The work with a evaporative condenser