  • The work will last for 6 months
  • Scale of the work is more than $1 800 000.00
  • Montreal, Quebec
    • Replacement of the building’s cooling towers
    • Air-lifted into place by a helicopter fitted out specifically for this type of work

other Projects

Pete Morin Arena

Complete overhaul of the 80 tons refrigeration room that includes a energy recuperation system.

Vidéotron Beaubien

Installation of 63 Liebert evaporators for the new high-density server rooms.

1000 de la gauchetière

Complete installation of an air conditioning system for a 50-storey office tower, in addition to an artificial skating rink in the central atrium.