sectors : Data Centers/Telecommunication
  • The work will last for 12 months
  • Scale of the work is more than $800 000.00
  • Quebec, Quebec
    • Complete ventilation and air conditioning systems for server room
    • Multi-phase project in clean-room environment
    • Welding realised while servers were in operation
    • Special installation procedures
    • HEPA filtration during brazing operation

other Projects

Cummins Diesel

Office air conditioning and carbon monoxide removal.

Complexe DesJardins

Replacement of the building’s cooling towers. Air-lifted into place by a helicopter fitted out specifically for this type of work.

1000 de la gauchetière

Complete installation of an air conditioning system for a 50-storey office tower, in addition to an artificial skating rink in the central atrium.

Facebook