sectors : Institutional
  • The work will last for 3 years
  • Scale of the work is more than $20 000 000.00
  • Montreal, Quebec
    • Hospital consisting of more than one building, for a total of 10 storeys
    • Eequiring the installation of high-performance HVAC (heating, ventilation and air conditioning) systems
    • High levels of filtration, allowing air to be treated up to a 100% level in order to provide superior-quality air.
    • Technical and mechanical work was completed in the A and B Blocks, consisting of rooms for medical consultations, medical examinations, minor surgery and MRI scans.
    • Specific technology used for this project: chilled beams.
    • To see how work progressed during this project: http://cusm.ca/new-muhc/article/suivez-les-progres-construction-en-ligne.

other Projects

Complexe DesJardins

Replacement of the building’s cooling towers. Air-lifted into place by a helicopter fitted out specifically for this type of work.

Pete Morin Arena

Complete overhaul of the 80 tons refrigeration room that includes a energy recuperation system.

Ultima Foods

To increase the yogurt production, we installed additional ammonia compressors.