sectors : Industrial
  • The work last for 5 months
  • Scale of the work is more than $400 000.00
  • Terrebonne, Québec
  • New steel and metal surfaces’ treatment facility. ADF Group is a major producer of complex metal structure elements. This new facility will will allow the handling of oversized structural elements.

    Characteristics

    • Construction of the ventilation system with the constraints of overhead cranes on the whole surface of the plant.
    • Ventilation system 100% fresh air / 100% exhaust with a total capacity of 92 000 CFM.
    • Four evacuation chimneys of 25 metres high.
    • Ventilation of a compressor room with heat recovery.

other Projects

Letendre College

Complete installation of an air conditioning system for classrooms.

Cummins Diesel

Office air conditioning and carbon monoxide removal.

CHU Sainte-Justine

Installation of bifurcated axial fans specifically designed for hospital environments.