sectors : Institutional
  • The work will last for 1 year and 7 months
  • Scale of the work is more than $1 400 000.00
  • St-Laurent, Quebec
    • New installation of several ventilation systems for the entire building
    • LEED-NC, v.1.0, Gold-certified building
    • The mechanical rooms contain eight (8) modular units as well as two (2) fresh air systems with a thermal heat recovery wheel
    • One of the units is 3.58 meters high
    • Distinctive features: special architecture, working at heights, ceilings with different angles
    • Technology: Adjustable-angle long-throw jet nozzle diffusers.