sectors : Institutional
  • The work will last for 6 months
  • Scale of the work is more than $700 000.00
  • Montreal, Quebec
    • Installation of a redundant 400 tons refrigeration units.
    • Challenge : incorporation of a cooler in a very small place located in the mechanical room (required custom engineering plans)
    • A lot of coordination : no period with no air conditioning where tolerated