sectors : Data Centers/Telecommunication
  • The work will last for 12 months
  • Scale of the work is more than $800 000.00
  • Quebec, Quebec
    • Complete ventilation and air conditioning systems for server room
    • Multi-phase project in clean-room environment
    • Welding realised while servers were in operation
    • Special installation procedures
    • HEPA filtration during brazing operation