sectors : Data Centers/Telecommunication
  • The work will last for 12 months
  • Scale of the work is more than $800 000.00
  • Quebec, Quebec
    • Complete ventilation and air conditioning systems for server room
    • Multi-phase project in clean-room environment
    • Welding realised while servers were in operation
    • Special installation procedures
    • HEPA filtration during brazing operation

other Projects

MUHC - McGill University Health Center

Hospital consisting of more than one building, for a total of 10 storeys, requiring the installation of high-performance HVAC (heating, ventilation and air conditioning) systems, with high levels of filtration, allowing air to be treated up to a 100%

Major agrifood corporation

New warehouse with 384 tons of refrigeration. 40 evaporators with hot gas defrost cool the distribution center. The freezer is maintained at -18C and the rest is at 4 C. The work with a evaporative condenser.

Complexe DesJardins

Replacement of the building’s cooling towers. Air-lifted into place by a helicopter fitted out specifically for this type of work.

Facebook
LinkedIn